OYEN WIND TRANSMISSION PROJECT
PROJECT OVERVIEW
The proposed Oyen Wind Transmission Project (the Project) is located approximately seven kilometres (km) northwest of Oyen, Alberta. The Project will connect a customer’s new generation facility to the electrical grid.
The Project will consist of constructing approximately six (6) kilometres (km) of single-circuit 240 kilovolt (kV) transmission line (to be called 9L26) along the unused eastside of existing steel lattice structures as well as completing alterations to the existing 959S Lanfine substation. The Project also consists of constructing approximately 4.7 km of single-circuit 240 kV transmission line (to be called 9LA26) which will connect the customer’s substation to the proposed 9L26 transmission line in a radial configuration.
-
TIMELINE
February 2026 - Facilities completed and operating
November 2025 - If approval granted, construction begins
December 2024 - Facility application filed with Alberta Utilities Commission (AUC)
April 2024 - Project Update notification to stakeholders
January 2024 - Project Update notification to stakeholders
September 2023 - Consultation began
September 2023 - Project Update notification to stakeholders
April 2023 – Notification to stakeholders
-
PROJECT INFORMATION
April 2024
January 2024
September 2023
- Project Update Notification Package
- Proposed Route Mosaic Maps
- Facility Detail Maps
- Proposed Site Layout Diagram
April 2023
- TRANSMISSION PROJECT FACT SHEETS
- EXTERNAL RESOURCES