OYEN WIND TRANSMISSION PROJECT
PROJECT OVERVIEW
The proposed Oyen Wind Transmission Project (the Project) is located approximately seven kilometres (km) northwest of Oyen, Alberta. The Project will connect a customer’s new generation facility to the electrical grid.
The Project will consist of constructing approximately six km of single-circuit 240 kilovolt (kV) transmission line (to be called 9L26) along the unused eastside of existing steel lattice structures as well as make alterations to the existing 959S Lanfine substation.
-
TIMELINE
February 2026 - Facilities completed and operating
November 2025 - If approval granted, construction begins
July 2024 - Facility application filing with Alberta Utilities Commission (AUC)
April 2024 - Project Update notification to stakeholders
January 2024 - Project Update notification to stakeholders
September 2023 - Consultation began
September 2023 - Project Update notification to stakeholders
April 2023 – Notification to stakeholders
-
PROJECT INFORMATION
April 2024
January 2024
September 2023
- Project Update Notification Package
- Proposed Route Mosaic Maps
- Facility Detail Maps
- Proposed Site Layout Diagram
April 2023
- TRANSMISSION PROJECT FACT SHEETS
- EXTERNAL RESOURCES
Questions? For more information on this project, contact ATCO toll-free at
1 855 420 5775 or by email at consultation@atcoelectric.com.